Tag Archives: construction san bernardino

sbX Construction Update for Oct. 29- Nov. 2

The sbX weekly construction update lists the places, dates, times and details of construction activity currently taking place in San Bernardino in preparation for the sbX bus rapid transit project.

Kendall Drive and Palm Avenue Park-and-Ride-Facility

  • Parameters: South of Kendall Drive and Palm Avenue intersection
  • Day Work: Mon. – Fri. from 7 a.m. to 4 p.m. daily
  • Specifics: Grading Activities, landscaping activities, electrical activities
  • LANE CLOSURE: No traffic control in effect

CSUSB

  • Parameters: New bus station location on campus
  • Day Work: Mon. – Fri. from 7 a.m. to 4 p.m. daily
  • Specifics: NA
  • LANE CLOSURE: No traffic control in effect.

Marshall Blvd. Park-and-Ride Facility

  • Parameters: Northeast & northwest corners of E Street and Marshall Blvd.
  • Day Work: Mon. – Fri. from 7 a.m. to 4 p.m. daily
  • Specifics: Work on bus pads continues, parking lot construction, electrical activities, lighting activities
  • LANE CLOSURE: Traffic control in effect

E Street

  • Parameters: Select locations between 10th Street and Hospitality Lane
  • Day Work: Mon. – Fri. 7 a.m. to 4 p.m. daily
  • Night Work: Mon. – Fri. from 9 p.m. to 7 a.m. nightly
  • Specifics: Utility relocations, driveway, sidewalk, curb and gutter work, domestic water work, storm drain activities, traffic signal activities, electrical activities
  • LANE CLOSURE: Traffic control in effect in some areas along E Street between 10th Street and Hospitality Lane.

 Hospitality Lane

  • Parameters: Select locations between E Street and Tippecanoe Avenue
  • Night Work: Mon. – Fri. from 10 p.m. to 7 a.m.
  • Intermittent Day Work
  • Specifics: Electrical activities, traffic signal activities, landscaping removal activities, irrigation activities
  • LANE CLOSURE: Traffic control in effect along Hospitality Lane between E Street and Tippecanoe Avenue.

 Various Bus Station Locations

  • Parameters: Little Mountain Drive, Shandin Hills Drive, Marshall Boulevard, Highland Avenue, Baseline Street
  • Day Work: Mon. – Fri. 7 a.m. to 4 p.m. daily
  • Night Work: Mon. – Fri. from 9 p.m. to 7 a.m. nightly
  • Specifics: Platform structure activities, curb and gutter work, storm drain construction, bus pad construction, utility activities
  • LANE CLOSURE: Traffic control in effect at some locations.
To establish a safe work environment for crews and the public, the construction crew has implemented traffic control measures that allow for at least one lane in each direction to be open during construction. Maintaining access to businesses is a high priority as part of this project. As such, signage is placed throughout the corridor to inform the public that they are open for business.


About sbX

The sbX Bus Rapid Transit (BRT) Project is the first-of-its kind express service to be constructed in the Inland Empire. It is the beginning of an intermodal public transit system in the San Bernardino Valley that will help reduce vehicle congestion while providing the public an environmentally friendly alternative that is sophisticated, cost effective, and time efficient.

The 15.7-mile corridor spans between northern San Bernardino and Loma Linda. It will include 16 art-inspired stations at key university, government, business, entertainment and medical centers as well as four park-and-ride facilities.

Visit the Omnitrans sbX Facebook page!
http://facebook.com/omnitrans.sbx

sbX Construction Alert for August 27th – August 21st

The sbX weekly construction update lists the places, dates, times and details of construction activity currently taking place in San Bernardino in preparation for the sbX bus rapid transit project.

Kendall Drive and Palm Avenue Park-and-Ride-Facility

  • Parameters: South of Kendall Drive and Palm Avenue intersection
  • Day Work: Mon. – Fri. from 7 a.m. to 4 p.m. daily
  • Specifics: Work on park-and-ride facility continues.
  • LANE CLOSURE: NA

CSUSB

  • Parameters: New bus station location on campus
  • Day Work: Mon. – Fri. from 7 a.m. to 4 p.m. daily
  • Specifics: Prep for roadway work of August 27th.
  • LANE CLOSURE: Traffic control in effect.

Marshall Blvd. Park-and-Ride Facility

  • Parameters: Northeast & northwest corners of E Street and Marshall Blvd.
  • Day Work: Mon. – Fri. from 7 a.m. to 4 p.m. daily
  • Specifics: Prep for grading of parking facility
  • LANE CLOSURE: Traffic control in effect

E Street

  • Parameters: Select locations between 10th Street and Hospitality Lane
  • Day Work: Mon. – Fri. 7 a.m. to 4 p.m. daily
  • Night Work: Mon. – Fri. from 9 p.m. to 7 a.m. nightly
  • Specifics: Driveway, curb and gutter work continues, electrical activities, street light activities
  • LANE CLOSURE: Parking and lane nearest the curb along the east side of E Street between 10th Street and 6th Street has been eliminated. Traffic control in effect on east and west side of E Street throughout the corridor.

 Hospitality Lane

  • Parameters: Select locations between E Street and Tippecanoe Avenue
  • Night Work: Mon. – Fri. from 10 p.m. to 7 a.m.
  • Intermittent Day Work
  • Specifics: Median removal between Tippecanoe Avenue and east of East Carnegie Drive, driveway, curb and gutter work continues including sidewalk removals, storm drain activities, water meter relocations, electrical activities, street light activities
  • LANE CLOSURE: North side of Hospitality Lane nearest the curb is closed.

 Various Bus Station Locations

  • Parameters: Little Mountain Drive, Shandin Hills Drive, Marshall Boulevard, Highland Avenue, Baseline Street
  • Day Work: Mon. – Fri. 7 a.m. to 4 p.m. daily
  • Night Work: Mon. – Fri. from 9 p.m. to 7 a.m. nightly
  • Specifics: Platform structure activities such as rebar placement and concrete slab curing; storm drain activities.
  • LANE CLOSURE: Traffic control in effect at some locations.
To establish a safe work environment for crews and the public, the construction crew has implemented traffic control measures that allow for at least one lane in each direction to be open during construction. Maintaining access to businesses is a high priority as part of this project. As such, signage is placed throughout the corridor to inform the public that they are open for business.


About sbX

The sbX BRT Project is the first-of-its kind express service to be constructed in the Inland Empire. It is the beginning of an intermodal public transit system in the San Bernardino Valley that will help reduce vehicle congestion while providing the public an environmentally friendly alternative that is sophisticated, cost effective, and time efficient.

The 15.7-mile corridor spans between northern San Bernardino and Loma Linda. It will include 16 art-inspired stations at key university, government, business, entertainment and medical centers as well as four park-and-ride facilities.

Visit the Omnitrans sbX Facebook page!
http://facebook.com/omnitrans.sbx

sbX Construction Update for June 30 – August 3

To establish a safe work environment for crews and the public, the construction crew has implemented traffic control measures that allow for at least one lane in each direction to be open during construction. Maintaining access to businesses is a high priority as part of this project. As such, signage is placed throughout the corridor to inform the public that they are open for business.

Kendall Drive and Palm Avenue Park-and-Ride-Facility

  • Parameters: South of Kendall Drive and Palm Avenue intersection
  • Day Work: Mon. – Fri. from 7 a.m. to 4 p.m. daily
  • Specifics: Work on park-and-ride restroom continues, Sidewalk grading
  • LANE CLOSURE: NA


CSUSB

  • Parameters: New bus station location on campus
  • Day Work: Mon. – Fri. from 7 a.m. to 4 p.m. daily
  • Specifics: Roadway work such as paving, pouring and concrete curing activities continue, work on bus passenger platform continues
  • LANE CLOSURE: Traffic control in effect.


E Street

  • Parameters: Select locations between 10th Street and Hospitality Lane
  • Day Work: Mon. – Fri. 7 a.m. to 4 p.m. daily
  • Night Work: Mon. – Fri. from 9 p.m. to 7 a.m. nightly
  • Specifics: Driveway, curb and gutter work continues, tree relocation, storm drain activities, electrical activities, street light activities, fire hydrant relocation activities, water meter relocation activities
  • LANE CLOSURE: Parking and lane nearest the curb along the east side of E Street between 10th Street and 6th Street has been eliminated. Traffic control in effect on east and west side of E Street throughout the corridor.
  • Please note: Properties impacted by water meter relocation activities will receive notification prior to service. 


Hospitality Lane

  • Parameters: Select locations between E Street and Tippecanoe Avenue
  • Night Work: Mon. – Fri. from 10 p.m. to 7 a.m.
  • Intermittent Day Work
  • Specifics: Driveway, curb and gutter work continues, landscaping activities, irrigation activities, electrical activities, street light activities
  • LANE CLOSURE: North side of Hospitality Lane nearest the curb is closed.
 

Various Bus Station Locations

  • Parameters: Little Mountain Drive, Shandin Hills Drive, Marshall Boulevard, Highland Avenue, Baseline Street
  • Day Work: Mon. – Fri. 7 a.m. to 4 p.m. daily
  • Night Work: Mon. – Fri. from 9 p.m. to 7 a.m. nightly
  • Specifics: Storm drain activities, and platform structure activities such as pouring slab, forming walls and erecting structure steel, irrigation activities
  • LANE CLOSURE: Traffic control in effect at some locations. 


About sbX

The sbX BRT Project is the first-of-its kind express service to be constructed in the Inland Empire. It is the beginning of an intermodal public transit system in the San Bernardino Valley that will help reduce vehicle congestion while providing the public an environmentally friendly alternative that is sophisticated, cost effective, and time efficient.

The 15.7-mile corridor spans between northern San Bernardino and Loma Linda. It will include 16 art-inspired stations at key university, government, business, entertainment and medical centers as well as four park-and-ride facilities.

Visit the Omnitrans sbX Facebook page!
http://facebook.com/omnitrans.sbx

sbX Bus Rapid Transit crews celebrate safety record

Six months ago, we began construction on our sbX bus rapid transit line. Despite the many challenges of working within an active transportation corridor, the GriffithCompany and Comet Electric joint venture construction team completed 50,000 man hours without a time-lost reportable incident.  That’s the equivalent of one person working 24 years without incident! The project has also brought jobs to 60 residents of the Omnitrans service area.

On July 12, sbX construction workers and staff took a brief break from the extreme heat and humidity to be recognized by project management for their exemplary safety record with a barbeque lunch.

Keep up with the latest sbX news. Join us on the Omnitrans sbX Facebook page at http://facebook.com/omnitrans.sbx for more great photos and articles!